Skip to content
Hanyani News Online Hanyani News Online Hanyani News Online
Hanyani News Online Hanyani News Online Hanyani News Online
  • Home
  • Local
  • Politics
  • Business
  • Sports
  • Tech
  • Entertainment
  • Opinion
  • Regional
  • World
  • Contact Us
  • Home
  • Local
  • Politics
  • Business
  • Sports
  • Tech
  • Entertainment
  • Opinion
  • Regional
  • World
  • Contact Us
Latest
Traditional Chinese Medicine Finds a Growing Place in Zimbabwe’s Healthcare Landscape
List of 24 Zimbabweans Believed Dead in Russia’s War Circulates Online
From Chaka to Mtukudzi: A Son’s Long Road to a Name
Mthuli Ncube Full 2027 Budget Presentation
Scammers target schools, colleges with fake AI summit
“He’s My Friend!”: Trump Greets Putin Warmly as Russian Bombers Probe Taiwan
GTA VI launch opens door for Zimbabwean gamers and streamers to cash in on esports boom
UZ warns students against selling morning-after pills, PrEP on campus
Cabinet Approves National AI Charter, Arts Council Reforms and Key Foreign Engagements
Illegal Sand Poaching Leaves Deadly Open Pits in Eyestone
Business

Zesa makes bid to pay US$1bn debt in yuan

By Mthandazo Nyoni
November 9, 2026
0

Zesa wants to convert a US$997,7 million loan from the China Export-Import Bank (CEIB) into Chinese yuan. The loan finances the expansion of Hwange Thermal Power Station. The utility hopes the move will ease its debt-servicing pressures.

What the restructuring proposes

Hwange Electricity Supply Company (Pvt) Limited (Hesco) put forward the proposal. It would change the loan’s denomination from United States dollars to Chinese renminbi (RMB). It would also extend the grace period by four years and push the repayment deadline to April 28, 2052.

“The proposal seeks to extend the grace period by four years to April 28, 2029, extend the loan repayment period by ten years to April 28, 2052, and convert the loan denomination from United States dollars (USD) to Chinese Renminbi (RMB),” Zesa said in a document.

Expected benefits for Hesco

Zesa says the changes will ease immediate cashflow pressure and reduce annual repayments. Hesco expects about US$207 million in cashflow relief during the extended grace period. The restructuring would also cut annual debt-service obligations by an estimated US$22,5 million between 2029 and 2052.

Zesa said the changes would “significantly strengthen Hesco’s financial position.”

A shift to yuan repayments should also reduce Hesco’s exposure to currency movements. “Converting the loan to RMB is expected to reduce foreign exchange risk associated with servicing a USD-denominated facility, improve compliance with repayment obligations, and eliminate exposure to penalty interest,” Zesa said.

How the loan came about

Hesco and CEIB agreed the US$997,7 million facility under a preferential buyer’s credit arrangement. It covers 85% of the engineering, procurement and construction contract that Hesco awarded to Chinese contractor Sinohydro.

Hesco did not draw down the full amount before the availability period expired on April 28, 2025. CEIB had disbursed US$672,4 million, which left US$325,3 million undrawn.

Why Hesco is restructuring

CEIB rejected applications to extend the availability period. Hesco then decided to pursue a restructuring. Its parent company, Zimbabwe Power Company, Zesa (Private) Limited, the Mutapa Investment Fund and relevant government ministries back the move.

CEIB’s response

CEIB and Sinohydro representatives discussed the proposal during a May 30, 2026 working visit to Hwange Units 7 and 8. The delegation reviewed the power station’s operational performance and assessed outstanding project works. It also considered Hesco’s proposed changes to the financing arrangements.

CEIB reportedly said it was favourably considering the proposal. No one has announced a final agreement. Zesa described the talks as an important step towards safeguarding the long-term sustainability of the loan and the Hwange expansion project.

The Chinese lender also recommended that Hesco take over customers currently pledged under existing financing arrangements once those facilities expire.

Zesa spokesperson Prisca Utete had not responded to questions by the time of going to print.


Reporting based on original coverage by Zimbabwe Independent.

Tags:

China Export-Import BankChinese yuanforeign debtHwange Power Stationloan restructuringMutapa Investment FundSinohydroZESAZimbabwe Energy Sector

Share this article to:

Other Articles
Previous

Major stock exchange’s crisis extends beyond uncertainty over ZiG: Analysts

Next

Invictus Moves Closer to Musuma-1 Drilling as Equipment Mobilisation Begins

No Comment! Be the first one.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Hanyani News Online is a dynamic digital media platform delivering accurate, timely, and engaging news coverage. From breaking local stories to global trends, we connect our audience with reliable information they can trust.

  • Home
  • About Us
  • Contact Us
  • Terms and Conditions
  • Privacy Policy
  • Copyright
  • Disclaimer
Support Hanyani News
Follow us on Socials
  • X
  • Facebook
  • YouTube
  • Instagram
  • TikTok
  • WhatsApp
Join One Of Our WhatsApp Groups Here
Join Now
©2026 Hanyani News Online. All rights reserved.